What is the timeline?
Fall 2022:
- New LMS online
- Sakai available for content migration only
Summer 2022:
- Training (continued)
- Self-paced videos
- Traditional training
- Documentation
- Data migration (continued)
Spring 2022:
- January
- Set up production instance
- February & March
- Transition Team established and begin planning
- Behind the scenes technical work
- April & May
- Canvas success manager and transition team begin project
- Critical SLU priorities (including, not limited to):
- Design SLU Canvas
- Communication plan to include timeline and milestones
- Policy decisions
- Sakai access
- Data retention
- Default options for accessibility/inclusivity
- Course migration options
- Export from Sakai to Canvas
- Canvas migration tool
- K-16 (3rd party) migration
- Process development
- K-16 cost limitations
- Outline criteria and processes
- Priority for Fall 2022 courses
- Export from Sakai to Canvas
- Training
- Self-paced videos
- Traditional training
- Documentation
- Identify content migration strategy
Fall 2021:
- Design and distribute RFP
- Exploration of sandbox environments
- Campus-wide vendor demonstrations TBA
- Distribute faculty survey
- RFP due November 5, 2021
- LMS team to review proposals and make decision by 12/3
- LMS team to present recommendation to ETC & FD committees on 12/8
Spring 2021:
- Develop capital budget request
- Set up sandbox environments
Fall 2020:
- Survey LMS market
- Arrange initial vendor demonstrations
- Develop outline of needs